Key Milestones

2015

2015 Awarded bizSAFE Enterprise Exemplary Award & bizSAFE Champion Award

Awarded the bizSAFE Enterprise Exemplary Award & bizSAFE Champion Award in bizSAFE Convention 2015, we are recognised by the Workplace Safety & Health Council (WSHC) to have demonstrated commendable WSH performance through the implementation of excellent risk management plans.
2014

Awarded Subcontractor’s Safety Recognition Award

Awarded Subcontractor’s Safety Recognition Award in Land Transport Authority 16th Annual Safety Award Convention, in recognition of our good workplace safety and health management.

Thomson Line Contract T228

Secured subcontract for the provision of excavation works at Thomson Line Contract T228 for the construction of Gardens by the Bay Station and Tunnels.

Changi Airport Terminal 4

Secured earthworks and soil improvement projects for the construction of Changi Airport Terminal 4
2013

Winner 2013 Singapore Enterprise 50 Awards

Our company was awarded 1st position and winner of the Singapore Enterprise 50 Awards in 2013. All Directors of Soon Li Heng Civil Engineering was present to receive the award on that momentous night.
2012

Awarded 2012 Singapore Enterprise 50 Awards

Awarded the 2012 Singapore Enterprise 50 Awards (15th position), we are recognised as the fifty most enterprising privately-owned local companies in Singapore.
2011

Achieved ISO 14001:2004 Certification

Obtained ISO 14001:2004 Certification for Environmental Management System and Workplace Safety & Health Council bizSAFE Partner Certification.

Downtown Line Stage 3 Contract 929 & Contract 932A

Secured 2 subcontract for the provision of excavation works at Downtown Line 3 Contract 929 for the construction of Kaki Bukit Station and Contract 932A for the construction of Geylang Bahru Station.
2009

Achieved OHSAS 18001:2007, ISO 9001:2008 & bizSAFE Star Certification

Obtained OHSAS 18001:2007 Certification for Occupational Health & Safety Management System, ISO 9001:2008 Certification for Quality Management System and Workplace Safety & Health Council bizSAFE Level Star Certification.
2007

Single Largest Trucks Purchase

Single largest purchase of 40 numbers of tipper trucks in support of Marina Bay Sands Integrated Resort projects.

Marina Bay Sands Integrated Resort

Secured projects for the excavation of the Marina Bay Sands Integrated Resort and District Cooling System.
2005

Circle Line Stage 1 Contract 828

Entrusted by Nishimatsu Construction Company and LTA to carry out the excavation works for Circle Line Stage 1 under Contract 828 for the realignment and construction of Nicoll Highway Station and Tunnels after the Nicoll Highway collapse.
2001

Kallang-Paya Lebar Expressway Contract 423

Secured our single largest contract for major underground as an earthwork sub-contractor for the construction of the Kallang-Paya Lebar Expressway (KPE) under Contract 423.
1999

North East Line Contract 701

Secured our second consecutive major LTA MRT railway project for the provision of earthworks at North East Line Contract 701 for the construction of Buangkok Green Depot.
1998

Secured 1st Major Railway Project

Secured our first major Land Transport Authority (LTA) Mass Rapid Transport (MRT) railway project as a specialist subcontractor for the provision of earthworks at North East Line Contract 704 for the construction of Serangoon and Woodleigh stations and tunnels
1994

Incorporation as Private Limited Company

Soon Li Heng Civil Engineering was incorporated on 26th September 1994 as a private limited company.
1980

Began specialization works

Moved up value chain and began specializing in civil engineering and excavation works
1975

Began Operation

Began operation as a transportation company of construction materials for civil engineering and building contractors.